Rashad – Abujibeiha – Kalugi Line Project

Rashad – Abujibeiha – Kalugi Line Project (Part 1)
  • Voltage :220 kilovolt
  • Line length : 145 kilometres
  • Present situation : Line has been identified
  • Implementation period : one year
  • Specifications : a 220 kilovolt double line on iron towers
  • Ground wires have two parts
  • Optical ground wire
  • Steel ground wire
  • Wire section area 240 sq. mm
Rashad – Abujibeiha
– Kalugi Line Project
(Part 2)
Al-Abbasiya substation
  • Type : conversion station with switches outside the station
  • Voltage : 220 /33/ 11 kilovolt
  • Capacity : two transformers with 40 megawatt capacity for each
  • Number of line entries and exits : 220 kilovolts = 7
  • Switch with switchboard – voltage: 33 kilovolt
  • Switch with switchboard – voltage: 11 kilovolt
Rashad substation
  • Type : conversion station with switches outside the station
  • Voltage : 220/ 33/ 11 kilovolt
  • Capacity 2 transformers with capacity 40 megavolt for each
  • Number of line entries exits: 220 kilovolt = 7, 110 kilovolt = 5
  • Switch with switchboard – voltage: 33 kilovolt
  • Switch with switchboard – voltage 11 kilovolt
  • Present situation : has been planned
  • Implementation period : one year
Contact National Electricity Corporation
Planning and Projects General Administration
Tel : +249 183782351
Fax : +249 183742403